Only 40% Of Land For Bullet Train Project Acquired

0

According to the information released in the Gujarat state assembly, only about 40% of the land has been required for the ambitious bullet train project, between Ahmedabad and Mumbai. The state government tabled the 3rd annual report 2018-19 of the central government’s flagship project.

Deputy Chief Minister of Gujarat Nitin Patel on Monday tabled the 2018-19 annual report of the ‘National High-Speed Rail Corporation Limited (NHSRCL)’. According to the report, only about 40% of the land requirement for the dream project of Prime Minister Narendra Modi, the bullet train between Ahmedabad and Mumbai, is acquired.

The acquisition is based on the joint measurement survey (JMS). The total land required for the entire project is 1,380 hectares, where 939.69 hectares fall in Gujarat, 431.2 hectare falls in Maharashtra and 8.70 hectares in Dadra and Nagar Haveli.

The NHSRCL company has obtained various environmental clearances like the CRZ clearance across the Narmada river in Bharuch district, the wildlife clearance for Thane Creek Flamingo wildlife sanctuary and Sanjay Gandhi National Park and Tungareshwar Wildlife Sanctuary.

The NHSRCL has also carried out tree transplantation at various places in Ahmedabad. According to the project, around 3,000 trees will be axed for the project in Ahmedabad.